In Progressive DB, is the final project cost and schedule commitment established as part of the selection process?

Prepare for the Design-Build Institute of America (DBIA) Exam 1 with our comprehensive study resources. Explore flashcards and multiple choice questions with detailed explanations to ensure success.

Multiple Choice

In Progressive DB, is the final project cost and schedule commitment established as part of the selection process?

Explanation:
In Progressive design-build, the selection phase focuses on the team’s qualifications, approach, and ability to collaborate to develop the project concept. The owner expects to refine the design and finalize cost and schedule as the design develops, not at the point of selection. Because the design evolves with input from the design-builder, final project cost and schedule commitments are not established during the initial selection; they are negotiated or locked in later, after more design detail is available.

In Progressive design-build, the selection phase focuses on the team’s qualifications, approach, and ability to collaborate to develop the project concept. The owner expects to refine the design and finalize cost and schedule as the design develops, not at the point of selection. Because the design evolves with input from the design-builder, final project cost and schedule commitments are not established during the initial selection; they are negotiated or locked in later, after more design detail is available.