CMAR procurement uses which statement about pre-construction services?

Prepare for the Design-Build Institute of America (DBIA) Exam 1 with our comprehensive study resources. Explore flashcards and multiple choice questions with detailed explanations to ensure success.

Multiple Choice

CMAR procurement uses which statement about pre-construction services?

Explanation:
In CMAR, the Construction Manager at Risk is engaged early and provides pre-construction services to the owner, bringing construction expertise into the design process. These services include early cost estimates, value engineering, constructability reviews, scheduling input, and procurement planning to shape the project so it can meet cost and timing targets. Because the CMAR arrangement centers on the contractor delivering these services, the pre-construction work comes from the contractor, not the owner or the architect, and it is a planned, required part of the process. This collaboration helps avoid costly redesigns later and supports establishing a reliable GMP.

In CMAR, the Construction Manager at Risk is engaged early and provides pre-construction services to the owner, bringing construction expertise into the design process. These services include early cost estimates, value engineering, constructability reviews, scheduling input, and procurement planning to shape the project so it can meet cost and timing targets. Because the CMAR arrangement centers on the contractor delivering these services, the pre-construction work comes from the contractor, not the owner or the architect, and it is a planned, required part of the process. This collaboration helps avoid costly redesigns later and supports establishing a reliable GMP.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy